- Client
- Roads and Transport Authority (RTA)
- Location
- Jebel Ali, Dubai
- Area
- 10,000 m²
- Service
- Flooring & Surface Treatment
A working bus depot has to keep running while its floor is replaced. We delivered 10,000 m² of epoxy flooring across the depot in coordinated sections, with substrate preparation, epoxy application, lane lining, hatched safety zones, bay numbering, signage and floor writing completed area by area so that operations continued throughout. The finished floor takes daily bus traffic, workshop loads and wash-down cleaning.
Scope of works
- Substrate preparation across 10,000 m²
- Epoxy floor coating
- Lane lining and hatched safety zones
- Bay numbering, signs and floor writing
- Phased execution to keep the depot operational